Godrej Aravya Estate Construction Status is in the new-launch and early site-development stage, and site work started after 20 October 2025. The blueprints of the project are finished, and the sizes of the plots are already fixed. The main gate of the project is finished now. The boundary work is in progress, along with the starting of road alignments, initial model plot zone preparation, and the setup of the project site office. Survey markings and plot demarcation are also underway across the 48-acre layout.
The construction status of a project shows its present progress stage. It gives buyers a clear idea of when the project will start and when it will be ready for ownership.
Godrej Aravya Estate has got RERA approval from the Karnataka RERA Board with the registration number PRM/KA/RERA/1250/301/PR/171025/008180, and the site development work is progressing in planned phases. The initial focus is on boundary walls, entrance gateways, internal road alignments, and infrastructure networks such as drainage and underground utilities.
As per the latest construction update of Godrej Aravya Estate in October 2025, the procurement of high-quality materials is in progress. Known for their dedication, Godrej Properties uses premium materials for all their projects. They will offer only durable projects to buyers that last long. In this new project, they have used only branded materials to offer the best living spaces, including long-life paving materials for internal roads, RCC drains, high-quality cabling for streetlights, and robust water and sewage infrastructure to support the plotted township.
Important Dates about the project are as follows,
The building work is separated into small phases. Then, a timeline is set for each phase. Every stage of the project will be closely monitored to confirm that it stays on schedule. Quality checks are also done at each step to offer the best quality living spaces.
| Sl No. | Project Work | Construction Start Date | Construction End Date |
| 1 | Formation Of Plots | 10-10-2025 | 17-08-2030 |
| 2 | Formation Of Road, Footpath, drainage, erection of Electrical poles | 10-10-2025 | 26-07-2030 |
| 3 | Power Supply Work (Transformer & Substation) | 19-12-2025 | 04-10-2030 |
| 4 | Plantation Work | 01-01-2026 | 10-08-2030 |
| 5 | Other Miscellaneous Work | 30-10-2025 | 31-10-2030 |
Godrej Properties is always known for delivering projects on time, and their new project, Godrej Aravya Estate, is no exception. Measures are taken to check if the progress is going on correctly in time. It is done so that the project is planned to be finished correctly on the given date.
The recent construction work is shown in photos in the project’s gallery. It will be regularly updated with new photos in 2 weeks, so that buyers can know what is going on at the project site.
Constant updates on the current construction status help buyers to track the project regularly and make sure that it is on the correct track. Regular updates will be given here about each construction stage till the completion of the project. Buyers who wish to know the current construction status can check this website